Audit of Sida-funded projects in Ukraine: what the donor requires
Sida requires an annual external audit. For project support the auditor reports under ISA 800/805 and also performs agreed-upon procedures under ISRS 4400 (Revised). The partner receives three documents: the independent auditor’s report, a management letter and an agreed-upon procedures report.

- Independent auditor’s report with the project financial report attached.
- Management letter: all findings, control weaknesses and prioritised recommendations, plus follow-up on findings from earlier audits.
- Agreed-upon procedures report under ISRS 4400 (Revised).
What the donor requires
- The audit is carried out every year. The partner procures the audit services, and the audit fee is part of the project budget.
- The auditor applies ISA and states this in the report. Project and programme support is reported under ISA 800/805, core support under ISA 700.
- Agreed-upon procedures under ISRS 4400 (Revised) are a mandatory addition: the auditor reports factual findings without an opinion.
- The responsible auditor is an authorised public accountant or equivalent, external and independent. The partner’s internal audit does not qualify.
- The responsible auditor may serve a Sida-funded project for no more than seven years and is then replaced.
- Sida’s terms of reference are attached to the agreement. The partner may add tasks with Sida’s consent but may not remove any.
What the auditor tests: prepare in advance
- The financial report is structured so that it can be compared directly with the latest approved budget.
- It shows budget execution for the period and cumulatively, and the opening balance equals the closing balance of the previous period.
- Exchange differences are disclosed along the whole chain, from the transfer of funds to spending in local currency.
- Salaries: supporting documents, records of time actually worked approved by a manager, income tax and social contributions.
- Suppliers and implementing partners are screened against the EU sanctions list.
- The unspent balance is reconciled to the accounting records and the bank account. In the final year the amount to be repaid is confirmed.
- Where funds are forwarded to partners, the organisation keeps evidence of its review of their auditors and audit reports.
How we run the engagement
ToR review in 1 day
Send us the grant agreement and the donor’s terms of reference. Within one business day we tell you the report format and the timeline.
Scope and proposal
We agree the scope, the document list and the dates with you. A proposal follows once we have reviewed the task.
Fieldwork
We test costs against the budget and the agreement, source documents, procurement, payroll and fund balances. We work remotely and on site across Ukraine.
Report
We discuss findings with management before the report is issued. Reports are prepared in English and Ukrainian. A typical engagement takes two to four weeks.
Sources
- Sida’s Requirements for Annual Audit, September 2023
- Sida’s Standard Terms of Reference for Annual Audit of Project/Programme Support including ISRS 4400 (Revised), version 1.3, April 2023 (annex to the agreement with Sida)
Audit requirements of other donors
Financial audit under ISA 805, CHF 100,000 threshold.
Financial, compliance and performance audit.
ISA 800 and ISA 805, including funds forwarded to partners.
Audited annual project statements, six-month deadline.
Two independent assurance options.
Proof of use of funds and audit.
Grant financial report and pre-submission review.
Expenditure verification for EU grants.
GIZ project audit requirements and documents.
Audits, spot checks and micro-assessments under HACT.
More on project and grant audits
Donor-funded, grant and earmarked projects: engagement formats.
Which report the donor needs and how to prepare.
How requirements differ between donors.
What clients ask most often
Who appoints the auditor for a Sida-funded project?
The cooperation partner. It procures the audit itself and gives the auditor the latest agreed version of the terms of reference, which are attached to the engagement letter.
How does an ISRS 4400 report differ from an audit report?
In an audit report under ISA 800/805 the auditor expresses an opinion on the financial report. In an agreed-upon procedures report under ISRS 4400 the auditor only states what was found for each procedure, without an opinion or recommendations. Sida requires both.
What happens after the management letter is issued?
The partner prepares a management response with an action plan for each finding. Sida may reclaim funds it considers ineligible, so the response is best prepared together with the auditor.
Get a proposal